OSLO (Reuters) - The NorNed subsea power cable connecting Norway and the Netherlands will remain offline for "complex" repairs until Aug. 1, Norwegian grid operator Statnett said late on Tuesday.

Operators extend Norway-Netherlands power cable outage to August for repairs

OSLO (Reuters) – The NorNed subsea power cable connecting Norway and the Netherlands will remain offline for “complex” repairs until Aug. 1, Norwegian grid operator Statnett said late on Tuesday.

The cable with a capacity of 723 megawatt between the two countries has been offline since May 6.

“Investigations have shown that a part of the cable has to be exchanged,” Statnett said in a message to market participants.

The fault has been detected in a section just 30 metres from land running in the shallow Wadden Sea off the Dutch coast, which made the repairs “complex”, as the location rules out the use of offshore vessels or equipment, the company added.

Statnett has warned the south of Norway faced a “pressed” market situation this autumn due to low hydro reservoir levels and might have to rely more heavily on electricity imports.

The cable is jointly operated by Statnett and its Dutch counterpart Tennet.

(Reporting by Nora Buli, editing by Terje Solsvik)

About the Author

Reuterscontributor

Reuters, the news and media division of Thomson Reuters, is the world’s largest international multimedia news provider reaching more than one billion people every day. Reuters provides trusted business, financial, national, and international news to professionals via Thomson Reuters desktops, the world's media organizations, and directly to consumers at Reuters.com and via Reuters TV. Learn more about Thomson Reuters products: